|
Archives
March 2001 Feature Story
For many homes television has become our window to the world. We all have our
favorite programs. We faithfully watch the ten o'clock news to catch up on today's
world events. We take for granted that when we hit that button and turn that
dial the NBC Peacock, standing ever so proudly, will show up on the screen.
But where does that peacock come from?
Standing at the corner of 455 N. Cityfront Plaza Drive, the 40-story, 1.1 million
square-foot NBC Tower plays host to the NBC Broadcast studios, their affiliate
WMAQ-TV Radio, and a myriad of other prestigious tenants including Navistar
and Brinks Hoffer.
As early as 1985 architects Skidmore, Owings and Merrill began plans for the
development of NBC Tower. As part of Chicago's 50-acre Cityfront Center, their
initiative was for NBC to harmonize with its nearby neighbors, The Tribune Tower
and the Wrigley Building. To accomplish this feat their plans called for the
building to be developed along classic lines with a 120-foot, 90-ton steel spire
topping off the building. Contractors Morse Diesel International chose Indiana
limestone as the most cost-efficient material for the exterior. An aggressive
work schedule had the tower completed in 1988, ahead of schedule and below budget.
Four of the eight engineers on staff that look after the NBC Tower 24 hours a day, 7 days a week. (L to R) Ruben Barajas, chief Engineer Tom Driscoll, Assistant Chief Ken Heklowski, and Engineer Bruce Mac Kowiak.
Guided by Chief Engineer Tom Driscoll and his staff of eight engineers, the
team covers the tower 24 hours a day, seven days a week. Because the building
is relatively new, reactive maintenance is minimal. Most of the work scheduled
is preventive maintenance. An annual preventive maintenance schedule is put
in place at the beginning of each year. On each Monday a maintenance report
is generated telling the department what work needs to be accomplished that
week. They will handle most jobs from adjusting a hot or cold temperature setting
for a tenant to changing filters, cleaning cooling towers, greasing fans and
changing locks as needed.
An MRI bar code system is used to track all completed barcode work. Each piece
of equipment is labeled with its own distinct bar code. As work is completed
scanners issued to each engineer on the shift are used to scan the equipment's
barcode. At the end of the day all the information is downloaded to the computer
where an accurate maintenance history is kept of all work performed on each
particular piece of equipment.
Engineer Bruce MacKowiak checks into the Trane Tracer Summit 1000 system.
While the City of Chicago views the property as one entity, the NBC Tower was
designed to function as two separate buildings ? NBC broadcasting and The Tower.
With that in mind we will look at each side of the building.
On the Tower side of the building eighteen Otis Elevators transport people
between floors. Decorated with mirrors and ornate woodwork, a ride to the floor
of your choice is a pleasant experience.
None surpasses the beauty of this building's interior. A 16-foot ceiling graces
the green marble and granite lobby greeting tenants and visitors as they enter.
Polished bronze fittings lend an air of elegance to an already elegant structure.
In keeping with today's technological advances a touch pad directory system
is located on the lobby wall enabling visitors to locate any tenant in the building
within seconds.
A mass grouping of antennas, satellite dishes and electronic receiving gear are mounted on the rooftop of the tower.
Calling upon Trane? Building Automation Controls Sales Engineer, Gayle VanOstern,
a determination was made to equip the building with a total Trane system. A
Trane? Tracer 1000 Building Automation System on the Tower side ensures that
the HVAC system runs efficiently. Approximately 1000 Variable Air Volume boxes
maintain temperature settings. Since all thermostats are read-only in the tenant
areas, Chief Engineer Driscoll makes all necessary changes with the Tracer computer
located in his office. 1999 brought about an upgrade to the Trane? Tracer Summit?
1000 System. Alleviating any Y2K compliance concerns with the computers, the
upgrade brought the building system into the new millennium without a hitch.
According to Driscoll, "The system works very well."
A total of six Trane? water-cooled hermetic CVHE Direct Drive CenTraVac? Chillers
have been installed. Of these, three 677-ton chillers using R-11 refrigerant
service this side of the building. Four air handling units use chilled water
coils and plenum heaters. The HVAC equipment is rounded out with 4 supply fans
and 4 exhaust/return fans with a total horsepower of 1250.
One of three 677 ton Trane water cooled hermetic CVHE Direct Drive CenTraVac chillers. The chillers use CFC-11 refrigerant. The entire chiller system is controlled through the Trane Tracer Summit 1000 system.
The NBC Tower is an all-electric building. ComEd supplies power via three main
feed lines into the building. One line is used for the office side, one line
for NBC and the third for backup. A 12KV service supplies power to 30 new dry-type
transformers located in various ComEd rooms within the building. This voltage
is then reduced to 480Y/277 and 208Y/120 volts and distributed through switchboards
and distribution panels on each floor. In the event of a power failure a 1500kW
Cummins emergency generator will handle computers, emergency lighting, etc.
until power can be restored. With energy efficiency being the topic of the day
ComEd has installed an Energy Tracker system. By monitoring energy usage within
the building the electric company knows how much energy is being used on a daily
basis. During summer hours should curtailment become necessary it can be accomplished
through the Energy Tracker system. Because the building is total electric, this
means heating is also run on electric. Perimeter boxes along the windows and
floor use Trane? constant volume fan powered boxes with 2-stage electric heating
coils.
The condensing towers atop the roof use a series of complex filtering sytems to keep water flow clean and free of foreign matter.
If walls could talk The NBC portion of the building without a doubt would
have a few tall stories to tell. Perhaps the two most talked about shows on
daytime TV are taped here daily, The Jerry Springer Show and The Jenny Jones
Show. People line up in a glass enclosed patron area unaware of all the equipment
necessary to make their audience experience a pleasant one.
The three remaining chillers are allocated to NBC Broadcasting, giving them
their own chiller plant. The three chillers, 125- , 250- , and 425-ton respectively,
using R-11 refrigerant, service this section of the building. In addition, four
air handling units, 5 supply fans and 5 exhaust/return fans with a total of
390 horsepower are in service. Otis Elevator also maintains 4 service elevators
as ornately decorated as those in the Tower as well as a freight elevator.
When the building was originally erected a Trane? Tracer 100 Building Control
Unit was installed for the NBC section. The NBC broadcasting floors are monitored
in much the same way as The Tower but with a smaller Trane? system. Chief Engineer
Driscoll and his staff are responsible for maintaining this equipment as well.
As mentioned above one of the three ComEd lines feeding into the building is
dedicated to NBC. Because of the nature of the business, a consistent, reliable
power feed is essential to this part of the building at all times. Emergency
generators located here also ensure that just short of the end of the world
NBC will broadcast to its viewing audience.
In the midst of all the preventive maintenance a four-year project is also
taking place. The building is currently undergoing a complete re-caulking. One
side of the building will be completed each year.
So while our "building within a building" operates its own chiller plant and
air handling units, and is supplied electricity through its own dedicated line
to floors one through six, there are still a few building systems that it must
share. One of those being the domestic water system.
Water is supplied by the City of Chicago through two 12" water lines piped
into a main pump room located on the lower level. Liqui-Trol Systems, Inc. installed
and maintains a constant pressure type pumping system for the building's domestic
water needs with a tap off for the fire pumps. Three fire pumps supply water
to six standpipe risers located in different areas of the building. Each riser
supplies water to numerous fire department valves located in easily accessible
areas on each floor. Risers are equipped with a Siamese connection. This will
enable the fire department to make use of an outside water supply should the
need arise. Each of these pumps have Fire-Trol control panels and the power
supply is backed up by the emergency generator. Fire protection is a priority
for Tom and his staff and they make sure that this equipment is running efficiently.
The fire control pumps are located in the lower level. Three pumps supply water to six standpipe risers located in different areas of the building. The entire system is backed with auxillary power generators.
The floors are protected with a typical wet sprinklering system to alleviate
potential disasters should a fire break out. The sprinkler system is fed by
a standpipe located in the south stairway with isolation valves on each floor
used to shut the water supply off in the event of a false alarm. All sprinkler
system control valves have tamper devices installed. Main risers and branch
lines have flow alarms.
Monitoring all of this is a Simplex Life Safety System located in the main
lobby. This system consists of a fire annunciation panel that alerts the engineer
of a potential problem and its exact location; a communication system provides
speakers in all elevators for communication with stranded passengers; floor
speakers enable an individual floor to be evacuated or the entire building if
necessary. Rounding out the Life Safety System is a fan status panel, stairway
door unlocking controls and a rotating beacon at the southwest entrance. Light
panels in the lobby show each elevator and what floor it is on. Security cameras
on the reception area desk monitor entrances and the parking garage hallway.
The NBC Channel 5 TV studio where broadcasts are seen throughout the day. .
The NBC Tower can stand as proud as it does thanks to its first-class tenants
and to the crew that keeps the building functioning at a first-class pace. Responsible
for this is Chief Engineer Tom Driscoll. His first job was at the Ritz Carlton.
From there he continued his journey to the Mandell Building where he was promoted
to the rank of Chief Engineer. In this business for the past 25 years, and currently
employed by Cushman Wakefield, property managers for NBC Tower, Tom witnessed
the resurrection of the building and has been there since the opening. Tom is
married and has a son and daughter. His hobbies, when he finds the time, include
boating, golfing and working on old cars. His current collection includes a
1965 Malibu SS, a '67 Corvette and a 1923 T-Bucket. And if that isn't enough,
he also works part time for the Rosemont Police Department.
Tom's right hand is filled by Assistant Chief Ken Heklowski. Ken graduated
from Northeastern Illinois University with a degree in education. Shifting gears,
so to speak, he received his engineering degree from Morton College and began
working with Tom at NBC when it opened. Ken is married with one daughter. His
hobbies include, fishing, fishing and fishing. Tom's left hand is helped along
by shift engineers John Connolly, Mike Faucher, Jason Fischer, Bruce MacKowiak,
Ben Adebayo and apprentice Reuben Barajas. And property manager Larry Atkins
oversees them all to make sure that when the TV dial is turned on, the peacock
stands just as proud today as it did the day before.
Archives
|