|
Archives
Energy Reduction Plan Focuses On High Rise Pump System
At what point in the life of a large building do facility managers decide to
replace
key mechanical systems? The answer to that question depends on many factors,
including the age and condition of system components, operational performance
and efficiency, and the cost and long-term advantage of system replacement.
These questions are routinely discussed by managers at Houston, TX-based
Trizec Properties, a large commercial real estate management firm. Trizec,
a new subsidiary
of Brookfield Properties Corp., is widely recognized as among the most committed
building owners to the cause of energy efficiency and conservation of natural
resources.
The open air plaza of the Figueroa at Wilshire plays host to a spectacular 36-foot-tall fire and water display.
In 2002, Trizec assembled a nationwide “Energy Team,” tasked with
the need to assess and reduce the firm’s overall energy costs. They also
hoped to develop a renovation model for other Trizec buildings, and - most
importantly - a strategic energy reduction model for other building owners
to follow. The
latter of these, ideally, would serve as a model for building owners nationally,
not just those that are Trizec owned.
Trizec’s incentive wasn’t entirely altruistic. They were spending
$100 million a year for electric energy to operate all of their buildings and,
for this structure, they expensed an additional $20,000 annually for domestic
water pump system maintenance, so the incentive and the benefits were very
real.
One of Trizec’s holdings is the fifth largest high-rise in Los Angeles,
located in the heart of Southern California’s financial district. Known
as Figueroa at Wilshire for the intersection it was built on in 1990, the 1.4
million square foot, 52-story office tower features a Brazilian Rose polished
granite exterior, two dramatic, 75-foot high atria lobbies with granite walls
and floors and an open air plaza with 36-foot tall fire and water feature.
According to Wayne Harner, Trizec’s VP of Engineering, the needs of this
building moved to the top of their list in 2005 following a rigorous energy audit
of all Trizec properties. Harner added that “multiple issues” - high
maintenance and energy costs, progressively deteriorating water pressure in the
building, proprietary controls that left them with few options, and apparent
mechanical fatigue to the old pump’s steel barrels - would be addressed
with the new pump system.
Elmer Brady, Lead Mechanic, inspecting shaft coupling between the motor and the pump.
Jim Krachmer, chief engineer for the building, chose Baldwin Park, CA-based
PumpMan Inc., a pump system maintenance, repair and new installation contractor,
to perform
the replacement and installation project. System design support was provided
by Derek Johansson, Delta-Q, Inc., the SoCal manufacturer’s rep agency
for Grundfos Pumps.
“We’d known for a few years that the old pumping system would have
to go,” said Krachmer. “We just didn’t know when we’d
tackle the job. The logistics of demolition and replacement, and accomplishing
it all within a very tight timeframe, were more daunting than the expense to
do it. The energy audit confirmed the need to get it done, and to move the
job to the top of the list.”
“Trizec’s emphasis, for years, has been keenly focused on energy
analysis and ROI,” said Krachmer. To put teeth into the analysis, the
company did before-and-after system monitoring of voltage and current.
Elmer Brady, Lead Mechanic, and Victor Ortiz, Field Technician, checking and tightening all connections.
“
Surprisingly, the key challenge wasn’t replacing the old equipment with
the new pumping station,” added Krachmer. “The tough part was to
make all of the changes - which we considered ‘major surgery’ - with
no apparent loss of service to the building’s many tenants. This was
one facet of the project that left no room for error.”
“
Setting the fine points of this plan - analyzing every step of the procedure
- took significantly more time than the actual installations,” said Eric
Skjarstad, president of PumpMan Inc. “We had so many meetings to develop
the details, that by the time we were ready to begin the work, there was almost
a sigh of relief.”
“
To assure continuous water pressure throughout the change-out process we had
decided on a two-phase installation for the new equipment based on low-zone,
and high-zone work,” said Mike Woodward, field supervisor for PumpMan.
He explained that the high zone extended from the discharge manifold to supply
water to floors 26-51. The low zone branches off the discharge manifold through
a pressure regulation station; everything downstream of this is considered
the low zone which feeds floors 1-26.
The building’s 15-year-old pressure-boosting pump station consisted of
two Syncroflo triplex booster pump systems - one for the low zone and one for
the high zone. The low zone system consisted of a 15 HP pump and two 30 HP
pumps. The high zone system consisted of one 30 HP pump and two 60 HP pumps.
All of
the pumps were vertical turbines using pressure reducing valves to control
discharge pressure.
“
The previous constant-speed booster pump systems were terribly inefficient and
over sized,” explained Johansson. “Pressure reducing valves were
required to reduce discharge pressure at each pump, avoiding dangerous over-pressurization.
This was very inefficient.
Eric Skjarstad, President, PumpMan, Inc., and Eric's stepson, Mike Woodward, Field Service Supervisor. Mike and Eric review the final checklist.
The old system discharged at 500 psi at the lower level while delivering
150 to 200 pounds of water pressure at the top, using multiple regulators,
and
pressure reducing valves every few floors. “In the new configuration, we were able
to reduce system discharge pressure to 380 psi, providing proper pressure to
the upper floors and eliminating the need for pressure reducing valves at the
pumps,” added Johansson.
“
The first phase of the project was to install a four-inch Cla-Val regulator station
in order to temporarily feed the low zone with the high zone pump system,” said
Woodward. “This allowed us to shut down the low zone booster pump system
and remove it from the mechanical room. With a few changes to the steel structure,
we were able to use the existing seismic pad from the low zone booster pumps
as the place to install the new Grundfos BoosterpaQ.”
Mike Woodward, Field Service Supervisor, adjusts the Low Zone Pressure regulating station. This Regulator Station reduces the pressure from the new Grundfos BoosterpaQ to the 1st-25th floors.
During phase one, PumpMan technicians installed a new pressure reducing station. “We
did this because, just as we planned, we used the existing high zone system to
maintain pressure throughout the whole building,” explained Woodward.
And, then, when we disconnected the low zone system and reconfigured the high
zone
piping to feed the pressure regulation station, the building water service
was shut down for just 12 hours.
“
This was a well planned and calculated move, with some risk, to have the entire
building rely on only one of its systems for a full week while the new system
was being assembled onto the site of the former low zone pump system,” said
Krachmer. “This was the critical point on which the system’s success
or failure swung, all in the effort to avoid any major business interruptions
to our tenants.”
Mike Woodward, Field Service Supervisor, and Elmer Brady, Lead Mechanic, test the control panel.
“
The next weekend, we shut down the building water service,” said Krachmer. “PumpMan
technicians then turned off the high zone, disconnected all of the piping,
and reconnected all of the domestic piping to the new Grundfos BoosterpaQ!”
Most of this work, orchestrated tightly to happen fast, was accomplished
between 10 p.m. on a Friday, and 6 a.m. the next day. A team of technicians
worked
efficiently to tie in the new high zone system piping to the existing building
piping. This
required draining down the entire building, disconnecting the piping and electrical
from the existing high zone booster pump system and connecting the new pump
system to the existing piping and reconnecting the main power and emergency
power to
the new system.
New Grundfos BoosterpaQ Variable Speed Booster Pump system and Low Zone Pressure Regulator Station, installatin complete.
“
On the high pressure side of the system we’re pumping at 380 psi but the
building engineer required a rating of 600 psi for safety,” explained Woodward. “Schedule
40, 316 stainless steel pipe was used to replace all of the high zone piping.
Type ‘L’ hard copper tube was used for the supply to the new system
as well as downstream of the pressure regulation station (low zone). After
a week of smooth pump operation, we were given approval to remove the old high
zone pump system from the mechanical room.”
Ultimately, PumpMan technicians removed the building’s existing High
Zone and Low Zone water booster pump systems and installed one Grundfos Quadruplex
BoosterpaQ.
View of new Grundfos BoosterpaQ Booster pump system showing the 6-inch suction and discharge piping, 6" stainless steel suction and discharge manifolds, pump isolation valves, pump check valves, and system isolation valves.
Today, the office tower’s domestic water pumping system receives water
from the city’s supply at 50 psi, increases it to 380 psi to move it
to the upper floors, and regulates the pressure down as it returns to street
level.
Because the old system was split into two zones, there were normally two pumps
running, even at periods of low demand. And because there was no speed regulation,
the motors ran at full speed, wasting large amounts of energy.
PumpMan installed a new PRV station to regulate pressure going to the ‘low
zone,’ and an automatic emergency power transfer switch that allows the
pumps system to operate at reduced capacity if the building loses its main
power supply.
Schematic drawings and plans are looked over. The installation needed to be well-orchestrated with little room for error while the building water system was shut down.
Today, says Johansson, the new system’s variable speed drive can power
any of the four pumps. Operation of the pumps is a lead-lag arrangement that
first activates one pump which speeds up and slows down as water demand changes.
Each of the four pumps is “rotated in” as the lead pump on the variable
speed drive. When demand dictates, other pumps come online at full speed, while
the lead pump continues to operate on the variable speed drive to maintain a
constant system discharge pressure. This system doesn’t require pressure
reducing valves for the pumps themselves, because the drive ensures that discharge
pressure doesn’t fluctuate by more than a few percentage points even
with quick changes in demand.
This 1.4 million square foot, 52-story office tower features a Brazilian Rose polished granite exterior and two dramatic, 75-soot high atria lobbies with granite walls and floors.
Another facet of the PumpMan installation was to enable the system to run
at reduced capacity powered by the building’s emergency power system. “We
installed an automatic emergency power transfer switch which was wired into
the pump station. This was important for tenants, but critical for the rooftop
equipment
where we supplied make-up water for ten cooling towers, said Krachmer.
According to Derek Johansson, the new pump stations will virtually eliminate
maintenance costs. Running only one pump on a variable speed drive will greatly
reduce energy consumption and is expected to extend pump life and performance.
An added benefit is that noise levels were reduced significantly.
The energy and maintenance savings have been measurable, and included some
good surprises. “Prior to the project, we expected to save between $15,000 and
$20,000 in operating costs. But during this first year of operation, Jim saved
about $20,000 for energy used to power the booster pump system, and another $20,000
in maintenance to it,” concluded Krachmer. “We were repairing the
old system routinely, and that became a huge expense that we’ve now eliminated
entirely.”
Archives
|