|
Archives
Serving Chicago - Then and Now
The list reads like a Who’s Who of Chicago - The Monadnock Building,
The Shedd Aquarium, The John Hancock, Midway Airport, One Magnificent Mile
and from
top hotels to companies like Caterpillar, Grainger, Nabisco and Allstate. The
one thing they all have in common: Chicago Tank Lining.
The Chief Engineer recently had the opportunity to speak with Ken Brand from
Chicago Tank Lining on some of the more memorable jobs they have been on. We
also learned a little about where the company came from and where they see
themselves headed in the future.
To talk about Chicago Tank Lining is, in many respects, to talk about the
history of Chicago. But the beginning actually brings one to Bridgeport, Connecticut,
where a thriving Oil Burner Service business began in the mid-1950s.
Small, 275-gallon tanks sitting under a port, in the backyard or in a basement provided fuel oil for heating and hot water and a start for Chicago Tank Lining.
Around that time many of the homes and businesses used fuel oil to provide
heat and hot water. Fuel oil was stored in small, 275-gallon tanks in their
backyard,
under the porch, or in a basement. Shell was one of the main suppliers of oil
on the East Coast and they had recently introduced a detergent into the fuel.
“
The detergent was beautiful,” recalls Ray Brand, founder of Chicago Tank
Lining. “The pumps were clean, the filters spotless. But then all the tanks
started leaking - like an epidemic.” What no one had realized was that
the detergent was cleaning all the sludge and residue from the tank bottoms
and the trace amounts of water in the fuel was now corroding the clean steel.
The question then became, How do we prevent this from happening?
The answer was found at a trade show where the Brand brothers stumbled upon
a relatively new technology for repairing leaking tanks - 100% solid epoxies.
These epoxies were not your run-of-the-mill coatings or other thin, solvent-based
epoxies. They were very thick, difficult to work with and costly. But when
applied properly, they were almost indestructible and virtually corrosion proof.
The
Brand brothers weren’t sure what to make of this new material or what
it could do, but they knew they stumbled upon something great.
A rusted out Metro van sits as a reminder of how Chicago Tank began in Chicago. A small tank welded into the back of the van served to hold fuel oil while the 275 was repaired.
Applying this material to a 275, as the tanks were known, was fairly simple.
Chicago Tank had a couple of small International Harvester Metro Vans like
the one pictured below. “As I recall,” Ken said with a chuckle, “the
photo pretty much looks like the same condition as our van was at the time.” A
small tank was welded into the back of the Metro and when the serviceman arrived
at the job, he would pump the fuel out of the tank and into the truck.
He would then disconnect the 275, flip it upside down and grind the bottom.
He applied the red, gooey, taffy-like epoxy with gloved hands, embedded fiberglass
as required, and set heat lamps over the coating. After lunch, they would flip
the tank over, put the oil back in and go home.
Signing on as a franchisee, the Brand brothers began to coat the bottom of
every 275 they could find. They lined leaking and non-leaking tanks as well,
and provided
a 20-year guarantee. With things working out so well, two of the Brand brothers
decided to head west and give it a go in Chicago.
(L to R) Ken Brand and Warren Brand stand in front of one of their trucks, a far cry from the Metro vans the company began in.
Ray and Al Brand went to work lining “275s” and providing their 20-year
guarantee throughout Chicago. One of the first organizations they joined shortly
after reaching Chicago was the Chief Engineers Association. Ray remembers attending
meetings and making many good friends throughout the years. Ken told us that
the last guarantee call came in about 15 years ago from an elderly woman on the
West side. “I remember the call,” said Warren Brand, Director of
Marketing and Sales. “I couldn’t believe it. She faxed over the
guarantee letter and I think it was in the 19th year of the guarantee. So,
of course, we
honored the guarantee and went and made the repair. She gave us the guarantee
letter as a keepsake.”
The market began to change as natural gas use became more prominent. Soon
the way of the “275s” passed and Chicago Tank Lining got to work
finding new applications for their coatings.
As we took our virtual walk down Michigan Avenue we asked what was the most
challenging job that Chicago Tank had ever faced. Their answer was the Chicago
Board of Trade.
The floor of a cooling tower located on the John Hancock building gets prep work done before the coating is applied.
The year was 1990 and the Chicago Board of Trade building had a problem.
Three domestic water tanks in the 64-year-old building needed lining. The two
on
the 23rd floor were not a problem because they could be lined one at a time
during
normal working hours. But there was one on the 43rd floor that had to be lined
over a weekend so as not to interfere with futures trading.
Chicago Tank met with the CBOT and drafted a plan to line the tank over Memorial
Day weekend. It was vital that the work be completed in one weekend so as not
to interfere with the market’s opening the following Tuesday. The 43rd
floor tank supplied the water for the critical office space and various cooling
systems. After thoughtful planning and organizing, the schedule was set. It
was a risky project, but Chicago Tank Lining was prepared. In the event that
something
went not as planned, contingency plans were put in place.
The cooling tower floor after the coating application.
Set-up began on Thursday. By Friday, as CBOT employees ended their day and
headed off to enjoy a three-day weekend, Chicago Tank personnel began their
three-day
weekend. Work began by running over 1,000 feet of air hose from the diesel
compressor on the ground level in, around and throughout the building to power
the equipment
on the 43rd floor and access the tank.
Work began by draining, cleaning and drying the tank. Abrasive blasting began
around 9 p.m. Friday night. The tank was sprayed at 3 a.m. on Saturday morning,
tested by Sunday morning and ready on Monday, one full day ahead of schedule.
No contingency plans were needed - the job went as planned. To this day, the
coating has required no maintenance whatsoever.
As we talked they recalled the Harris Bank Building. A cooling tower basin
over 100 feet long had been leaking and Chicago Tank was asked to bid on the
project.
Unfortunately the job was awarded to another contractor.
As Chicago Tank Lining enters the swimming pool market they tackle a most challenging project at the Peninsula Hotel in New York.
“
However,” recalls Warren, “I remember getting a call about a year
later that there was a problem with the new coating. I went down to inspect the
basin and could take a piece of the coating and simply peel it off like a banana
skin.” The entire coating required removal. “And, we had to do it
in the winter time,” Warren told us. He went on to say that there were
now holes in the basin and the coating was difficult to remove. The job was
completed and much to their credit, there has not been a problem since.
Preparations begin for installation of the Pool Armor lining in the Peninsula Hotel. Stairs into the pool are being prepared for the coating.
So, we had heard about the most challenging job. The next question: Who holds
the oldest tank lining that you have done? Warren answered, “One of our
oldest tank linings that we know of is in a concrete tank at CBS. We lined it
some time in 1980. Ken remembered that the tank was over a recording studio and
they put a red light in the room. Whenever the red light turned on, we had to
stop operations. “The coating has never required an ounce of maintenance
and will outlast all of us,” Warren added.
A picture of the stairs after Pool Armor has been applied.
“
People constantly underestimate what can be done with the new materials on the
market today,” Warren said. Which is one of the problems Chicago Tank faces. “We’re
running out of tanks,” Warren quips.
Most recently Warren received an unusual call from the Peninsula Hotel in
New York. They had a very old steel pool that had been lined with some type
of
fiberglass material that had failed in various areas. “I’ve never seen a standard
fiberglass system work well in a pool,” Warren told us.
A view of the deep end of the pool as it is readied to be filled once again.
The Peninsula was unable to find anyone who knew what to do with the pool
and they had heard about Chicago Tank Lining after the company had completed
work
at the Peninsula here in Chicago. New York sent photos and dimensions and Warren
wrote up a detailed specification of what he thought should be done. Branching
out beyond tank linings, Warren wrote the specification using their proprietary
new product called Pool Armor.
“
The next thing I knew, they wanted to know how fast I could fly out to review
the pool.” Warren met with about a dozen people from architects to project
managers, building owners and engineers and a local artist. The Peninsula had
commissioned the artist to create a unique pattern in the pool. After explaining
to the artist that normal paint could not be used because of the harsh environment
in a chlorinated pool, Warren was able to figure out a way to accomplish the
artist’s goals with different colors and grades of Pool Armor, but time
was short.
Guests at the Peninsula Hotel, New York, can enjoy a leisurely swim in the newly lined pool.
“
The Peninsula was under the gun in terms of getting the work done. I put together
a detailed specification and budget plan and got a call from the architect with
the go-ahead,” Warren told us. Unfortunately, the artistic design the
Peninsula wanted would have added additional days to the timeline so it had
to be left
out. The project was completed and the pool put back into service within two
weeks.
Warren Brand is seen doing an underwater repair with Pool Armor. Warren has been YMCA and PADA certified in order to wear scuba gear to perform such repairs.
One of the advantages of Pool Armor is that it can be repaired underwater. “It’s
not easy,” Warren told us. “And it’s not the most beautiful
repair, but it’s functional and will typically get us through until the
next time we can get into the pool to conduct proper repairs.
Over the years, Chicago Tank Lining has gone from lining small, backyard
tanks to lining underground gasoline tanks, hot and cold water tanks and everything
in between. But their future, they believe, lies in servicing their existing
customer base, finding new customers, and expanding into swimming pools.
We
found it hard to believe that during our trip down Michigan Avenue it was
nearly impossible
to pass a building, or certainly a block, that Chicago Tank Lining had not
worked in.
Archives
|