|
Archives
Mission: Cooling Is Critical
When the Chicago Board of Options Exchange moved into its new building in
1984, its infrastructure was designed to accommodate all aspects of the daily
trading
activity at the exchange. Architects and contractors designed the building
with the highest standards available at that time. What they didn’t count on
were the rapid advancements in technology that would greatly impact the way business
would be conducted at CBOE in the years to come.
Home to several thousand traders, the trading floor at CBOE combines electronic and open outcry into one environment. Over the years, changes in the trading floor heat load necessitated a close look at the age and operation of the building's infrastructure.
Nearly twenty-five years later, the time had come for the facility’s
management to take a close look at the age and operation of their equipment
and determine
what could be done to make their building more efficient. The Chief Engineer
learned of some exciting changes that were being made at CBOE, 400 South LaSalle
Street, Chicago, and contacted Director of Engineering, Angelo Saccameno, to
update us on some of the major initiatives that have taken place at the exchange.
CBOE, the largest options exchange in the United States, was founded in 1973.
Today, CBOE trades options on approximately 1,900 individual stocks (i.e.,
Microsoft, IBM, and Google), 30 broad-based and sector specific indexes (i.e.
S&P 500,
Dow Jones Industrial Average, and Nasdaq-100) and over 100 Exchange Traded Funds
or ETFs (i.e., Diamonds, Spiders, and QQQ). Year-to-date in 2007, average daily
volume at CBOE is more than 3.5 million contracts per day, which accounts for
more than one-third of all industry volume. On a highly volatile day for the
markets this past February, CBOE traded nearly 7 million contracts, making it
the busiest day in the exchange’s 34-year history.
The Chicago Board Options Exchange is home to several thousand traders, brokers, clerks and exchange staff - all wearing brightly colored trading jackets.
Each day, CBOE’s trading floor is home to several thousand traders,
brokers, clerks and exchange staff - all wearing brightly colored trading jackets.
Trading
at CBOE is conducted through a Hybrid Trading System, a unique market model
that combines electronic and open outcry trading into one environment. Presently,
over 96% of all orders at CBOE experience sub-second electronic execution.
In 2006, this 385,000 sq-ft., 7 story building was still operating with all
the original equipment. Because CBOE deals in hundreds of millions of dollars
of
trading on a daily basis, the building is deemed a “mission critical” structure – meaning
this building is a vital cog, not only in the Chicago financial community but
in the global marketplace - and there must be no loss of power at any time. Most
of the building’s equipment has been parallel sourced, dual sourced,
and is dual fed. As such, it was time to evaluate the current condition of
the building
systems and determine what could be done to bring them up-to-date.
Technological changes in the way business is conducted at CBOE led the building's management to take a close look at the age and operation of building equipment.
Equipment designed 25 years ago had a specific heat load to process and rapid
changes in technology have moved the trading floor from a latent heat load
to a process load. Over the past two decades the trading floor population has
decreased
by almost 60%, leaving a latent heat reduction close to 50%. In contrast, the
process heat load had almost doubled. An infrastructure analysis by EnerG Associates,
LLC concluded the building’s design no longer fit with its current needs
and that more economical means to produce the cooling necessary for this “mission
critical” building should be explored.
The peace and tranquility of the courtyard adjoining the CBOE building belies the frenetic activity that takes place inside.
The first challenging part of any project is to get all the departments together
to communicate what their current needs are and what they project they may
need in the future. When this was accomplished at CBOE, two very crucial points
became
apparent. First, because the process load of the data center was the driving
force in this building, it required so much cooling that the comfort level
of the latent load was too cold. The solution: create an independent cooling
loop
for the process load which enabled the data center to be cooled independent
of the whole building. Second, because CBOE is a mission critical building,
its
mechanical systems require a high level of reliability. In the event of catastrophic
failure of cooling towers or chillers, a secondary means of cooling must be
available.
When fog covered the city the morning the cooling towers were to be placed on the roof, an alternative method of getting them there was needed. Gatwood Cranes undertook the challenge of placing a 360-ton crane with a 165-foot boom on the street to make the necessary lift on three separate occasions.
Due to the fact that CBOE never shuts down, the $3 million project was fast-tracked.
Begun in December of 2006, the final completions were made in June of 2007.
In the EnerG Associates analysis, it was determined that the cooling towers
were
in poor condition and unable to support the systems used year-round by the
chillers. Three new BAC 900-ton towers operating on variable speed drives were
installed,
allowing for future expansion of the load. A helicopter lift was instituted
as the best means of getting the towers placed and on-line as quickly as possible.
Unfortunately, on the day the lift was scheduled, Mother Nature decided to
present
a little challenge of her own. That morning, a fog covered the city and the
lift was scrapped. As a result, a second attempt was required and an alternate
option
was devised: using a crane to lift the towers. This option, however, involved
a multi-leveled coordination plan between CBOE, contractors, and neighboring
buildings to accomplish the task.
Two of the three cells in the new cooling tower in place. Standing next to the old unit, the new cooling tower shows how much technology has changed in 25 years.
Mechanical contractor, Anchor Mechanical, supported by Olympic Pipe, pre-fabbed
as much of the piping as possible. “With a mandatory shutdown of the building
for this phase of the work, we were under a tight schedule. It was a pretty intense
job,” according to Angelo. A 32-man crew came in, drained the system,
tie-ins were installed and the system was back online within 32 hours.
Several crane companies had been approached regarding the lift. Not one was
ready to take on the logistics of trying to lift the tower cells into place.
Nor were
they positive the street would hold the weight. Only one company, Gatwood Cranes,
felt they could handle the job.
A view from the top of the old cooling tower and old supply lines. Twenty-five years of service have taken their toll and it was time to replace them.
Now ready for the towers, on a Friday night, the surrounding streets were
closed, Gatwood Cranes came in and started assembling their 360-ton crane on
LaSalle
Street to prepare for the lift. The lift was completed on Saturday, and the
crane was dismantled and gone by Sunday, and come 8:30 a.m. Monday morning,
the Opening
Bell rang and trading resumed without a hitch. Within a week the system was
back online. For the next two consecutive weekends the same procedure was followed
until all three towers were in place and operating. At no time during the entire
process was cooling to the building ever lost.
To expedite the installation process, much of the piping was pre-fabbed by Anchor Mechanical, aided by Olympic Pipe. This is a picture of the new supply line piping.
We asked Angelo if anything about this job stood out in his mind. He replied, “I
like the challenge of any job, especially if someone tells me it can’t
be done.” He continued, “this wasn’t the only challenge of
the job. Next we had to figure out how to get a 900-ton chiller down to the
sub-basement.”
Seemed pretty fundamental: you lower it down the elevator shaft!
These photos show the chiller coming down the elevator shaft with the help of a gantry rigged to the 4th floor elevator shaft. It was lowered in three separate pieces.
The existing chiller plant consisted of two Trane 900-ton Centra Vac chillers
and one 500-ton chiller. Already running at full capacity, original plans called
for replacing the 500-ton chiller with a newer, more efficient 750-ton chiller.
By May of 2006, it was deemed necessary to increase the size of that new chiller
to a 900-ton Carrier 19EF 134a to allow for future expansion. “Technology
produces a different kind of heat load,” Angelo told us. “We knew
that if our technology was going to continue to grow, we needed to be prepared
to cool it,” he added. A gantry rigged on the 4th floor across the elevator
shaft allowed the chiller to be lowered down in three separate pieces. Angelo
likened it to trying to fit a square peg in a round hole, but it was a challenge
he was ready to face. Once in the basement, the chiller was re-assembled and
put in place. Another challenge conquered.
Once all the pieces were lowered down, the unit was reassembled and put in place.
The new infrastructure of the building has accomplished two critical missions
for the exchange. One, the data floor is now on its own cooling loop, separate
from the the base building space, thereby affording the opportunity to keep
the data center at a much cooler temperature than the occupied space. Two,
the staff
also now has the option of cooling the building as one big load. Should maintenance
on any piece of equipment be required, that portion of the loop can be isolated
and repairs can be made with no loss of cooling encountered.
Racks of serves transfer the hundreds of millions of transactions process daily at CBOE. Room for expansion was built into the plans to allow business to be conducted in the most efficient way possible well into the future.
CBOE maintains five independent terminals to five ComEd substations. In the
event that the power from all five leads is lost, a total of 2250 kVa of emergency
generator backup power is available strictly to fill the vital role of keeping
the trading floor operational. In the unlikely event that even the generator
backup power should fail, emergency quick-connect tie-ins were installed to
maintain
the high level of reliability important to this building. These tie-ins supply
the necessary valves and pipes to enable the engineering staff to install a
temporary 700-ton chiller outside of the building to provide cooling requirements
until
full service can be restored.
In the event that power from all ComEd feeds is interrupted, racks of batteries stand ready to supply power for emergency systems so that no downtime is experienced.
Improving energy efficiency was a large part of the project. By installing
a plate and frame heat exchanger, condenser water from one cell of the cooling
tower can be dropped to 40ºF chilled water when outside air temperature permits.
By using this method, energy savings will be realized because the exchange
will
not have to run a chiller yet will still be able to meet the critical load.
CBOE also undertook the installation of a new UPS system to support the data
center applications. The increase in heat load by the new system was taken
into consideration when plans for the upgrades were made. Also taken into account
was an increase in distribution racks for future needs. The cooling system
needed
to be able to handle an increase in heat load.
Lighting throughout the building was also examined. After EnerG Associates
concluded their audit, the 100-watt incandescent floodlamps used to light the
lobby were
replaced with 25-watt halogen floodlamps. Incandescent fixtures throughout
the facility were replaced with self-ballasted 15-watt compact fluorescent
lamps.
About two-thirds of the office areas had previously been retrofitted with T-8
lamps and electronic ballasts. The remaining areas were also retrofitted with
T-8 lamps.
When projects with a large scope like this are finished, Angelo’s staff
is not. CBOE is a 24/7/365 operation. His department oversees 99.9% of the structural
projects in the building including, but not limited to, chillers, air handlers,
cooling towers, domestic water, and lighting. Angelo reports directly to the
Vice President of Facilities, LuAnn O’Shea. Together, LuAnn and Angelo
analyzed each phase of this project, evaluated the viability and scope of work
to be completed, and concluded that this project was a positive and necessary
directive for CBOE to undertake. Angelo’s staff, consisting of Assistant
Chief Engineer Neil Daly and engineers Jim Kosirog, Mike Kordik, Gerald Reddy,
Brandon Sidler, and Tom Maher, all played a major and integral part in the
successful outcome of this monumental project.
In the end, several benefits were achieved in this project, most notably,
the building becoming more operationally efficient, saving money for the exchange;
upgrading the infrastructure to improve building conditions in both the comfort
level and process levels; and creating a payback time of 3.1 years. Through
comprehensive review and analysis, CBOE has prepared its building to meet the
needs of the
present, while planning for the challenges of the future - no small task in
today’s
rapidly evolving financial industry.
Archives
|