|
Archives
Pumping Up Big John
When the domestic water supply system at Big John, The John Hancock Center,
began to show its age, the innovative pumping/control system which was installed
did more than simply restore the system to its original state.
The cutting edge system design improved the overall performance and versatility
of the water supply system, reduced maintenance requirements, provided dual
redundancy to guarantee continued operation, and also improved the quality of
life for the residents.
Big John's construction started in 1965 and was completed in 1968. After more
than 30 years of service, the domestic water supply system which serves the
condominium portion of the building started to show its age. Although the system
was continuing to operate daily, maintenance costs were climbing, and it was
becoming increasingly clear that a major overhaul was imminent. The association
of condominium owners, formally known as The 175 E. Delaware Homeowners Association,
selected McGuire Engineers of Chicago to spearhead the renovation design project.
McGuire's principal engineer, Mr. Richard Sanecki, supervised the project, working
closely with Mr. Harry Budge, Chief Building Engineer, 175 East Delaware Place.
From an engineer's perspective, the 100-story John Hancock Center on north
Michigan Avenue at Delaware, is actually three separate facilities. Retail stores
and commercial offices occupy the space from the concourse level to the 42nd
floor. The 45th floor through the 92nd floor are residential condominiums. The
third facility, from the 93rd floor and above, house elevator systems, building
utilities, cooling towers, an observation deck, the Signature Room restaurant,
and the equipment required to operate the commercial television and radio stations
broadcasting from the building's transmitter towers.
Each of the facilities is responsible for its own utilities. The 175 E. Delaware
Homeowner's Association is responsible for the water system feeding 703 luxury
condominiums, each ranging in size from one bedroom units to ones which cover
75% of a given floor, the Signature Room restaurant, the radio and television
water cooled transmitters, and the buildings roof mounted cooling towers. As
originally designed, the water supply originates in city water mains below the
building which feed two 500 constant speed pumps in the concourse level of the
structure. These pumps pressurize the water and deliver it to a 30,000-gallon
water storage reservoir located on the 50th floor, which extends to the 52nd
floor.
The top of the reservoir serves as a utility space on the 52nd floor for the
pumping and control systems operated by the condominium association. The original
condominium water supply system used constant-speed vertical-turbine pumps,
submerged in and supported from the top of the reservoir. Four High-Zone pumps
were designed to serve the uppermost portion of the facility, and three Low-Zone
pumps were designed to serve the lower portion. Pressure output from these pumps
was controlled by individual pressure regulating valves, or on the discharge
nozzle of each pump. This was a common design during the period of time in which
the facility was constructed. An inherent flaw in this design stems from the
operation of the pumps during night-time and other low-flow periods. During
those periods, the pumps operated at full-speed, with relatively no flow, creating
a situation in which the internal pressures within the pumps themselves climb
to their peak. This excessive pressure, commonly known as Shut-Off Head, causes
considerable long-term stress and eventual damage to the pump casings and mechanical
shaft seals. This damage results in a high incidence of costly maintenance on
these pumps.
The old vertical turbine installation.
During his initial inspection of the facility, Dick discovered a very serious
problem. The interior of the 30,000-gallon reservoir was showing signs of advanced
stages of corrosion, which meant that its structural integrity was at risk.
Realizing that the reservoir was in dire need of repair, it would need to be
drained, dried, cleaned, and reconditioned in short order, to avoid a catastrophic
situation. Unfortunately, the reservoir was the only means by which the condominiums
could receive domestic water, and the reconditioning operation would take months
to complete. After analyzing the system's performance requirements, the flow
capacity required for the condominiums was recalculated to allow for modern
convenience items such as whirlpool tubs, bidets, and, multi-jetted showers
which were not in use at the time the original project was completed.
Prepared documents for the 175 E. Delaware Homeowners Association solicited
bid proposals for the required renovations. Following a review of the responses,
the association recommended Metropolitan Industries of Romeoville, Illinois,
to design and install the new pump/control system. Metropolitan recommended
that the out-dated design of the original pumps be replaced by a modified version
of their System 2100 Submersible-turbine pumps, and energy-efficient variable-speed
controls. The typical System-2100 design, which has been used with great success
in many downtown Chicago projects including the American Dental Association
building, utilizes horizontally mounted submersible-turbine pumps. For this
project, the pumps would be installed vertically, allowing multiple pumps to
be placed side by side, submerged in the reservoir.
"Reconfiguring the horizontally mounted pumps to a vertical configuration
was not a major problem. Instead of being short and wide, the system components
would be tall and narrow," said John Kochan Sr., chairman of Metropolitan. The
problem was limited head-room clearance. The 52nd floor pump room had a relatively
low ceiling height. The crowded room itself created many additional installation
difficulties. Due to the difficult nature of the installation caused by the
limited headroom and the need for closely coordinated on-site installation services,
Metropolitan contracted with the experienced services of Aspen Plumbing of Streamwood,
Illinois. The low ceiling prevented removal of the old pumps in one piece, and
installing the new pumps in one piece. Instead, the old pumps would need to
be cut out in sections, and the new pumps would require assembling in sections
on site. With technical assistance by Metropolitan, Aspen Plumbing's crew coordinated
the work with only a one-time shut down, which lasted only a few hours during
a non-peak period. During no time did the residential units loose their water
supply. In addition, never was the critical supply of cooling water to the roof-top
television and radio transmitters ever threatened. With the input and assistance
of Aspen, Metropolitan designed an ingenious piping arrangement designed to
allow draining of the crippled water reservoir, while guaranteeing uninterrupted
flow of water to all areas of the facility. This was a critical design requirement,
as the water supply is necessary to the operation of this facility 24-hours
per day. To allow the reservoir to be repaired, Metropolitan designed an innovative
dual-feed piping system. During normal operation, the new system will operate
in similar fashion to the original system. The basement water feed system supplies
water to the reservoir and the new pumps draw water from the reservoir.
(L to R) Harry Budge, John Kochan, Sr., Dick Kviz
Conversely, when the time comes to drain the reservoir for rehabilitation,
supply water from the concourse level pumps will be fed directly to the new
High-Zone pumps, completely by-passing the reservoir. Each of the new High-Zone
pumps was fitted with a special suction inlet assembly. In addition, a unique
reservoir by-pass piping assembly allowed supply water to go directly to the
suction inlet of each pump, instead of the reservoir. Finally, a new High-Zone
to Low-Zone pressure reducing station was installed to allow the Low-Zone fixtures
to be supplied with water provided by the High-Zone pumps. The new completed installation
Combined, these design features will allow the entire facility to operate without
either the reservoir or the Low-Zone pumps. It was crucial for the proper operation
of the system in reservoir by-pass mode that regulated pressure to serve the
High-Zone pumps. For this reason a temporary variable-speed control system was
installed on the 100-HP concourse level feed pumps. This system allows for steady
state flows using a transducer to monitor the system pressure, and adjust the
pumping rate based on system demand. All of the new system components are designed
and sized so that the reservoir and Low-Zone pumps could be taken out of service
for the extended time period necessary, while providing an uninterrupted water
source sufficient for the entire facility," said Kochan.
Because a variable-speed control system provides greater electrical efficiency
and reduces maintenance costs of the pump components, the owners have already
experienced substantial savings which may result in a system payback period
of as little as two to three years.
In addition to the pump/piping work in the 52nd floor pump room, Metropolitan
also provided a programmable logic control system, complete with a touch screen
operator interface panel, and seven variable frequency motor drives for all
of the new pumps. This method of operation allows for greater hydraulic control
of the flow and pressure by allowing the chief building engineer, Harry Budge,
to configure the systems operation and set-points when required for events such
as the current tank project.
Again, due to their experience and expertise in various rehabilitation projects,
all of the electrical work, including demolition of the original controls and
the installation of all of the wiring, conduit, and control components, was
contracted to Blaze Electric of Berwyn, Illinois.
The new systems have met all of the requirements of the association. The variable-speed
submersible pumps use less energy, require less maintenance, and permit the
rehabilitation of the reservoir to be accomplished without disrupting the water
supply.
An additional benefit of the new pumps was discovered near the end of the installation.
As work was being completed, a woman whose condominium is near the 52nd floor,
approached the crew and told them the old pumps were very noisy. "I don't
know what you did with the new ones, but they sure are quiet!"
Archives
|