|
Archives
Comprehensive Energy Savings Earns A+
By replacing the Student Union’s boilers with newer, more efficient equipment,
Boise State University has taken an important step in improving overall campus
operations. In May 2003, the university announced the formation of an energy-‘Performance
Contracting’ partnership with Siemens Building Technologies, Inc. Energy
Services. This follows already successful efforts by the university to reduce
energy costs by $250,000 annually through avoided utility consumption.
According to David Naccarato, Siemens account executive, Boise State’s
sweeping initiative is fueled by a desire to steward funds responsibly. Virtually
all facets of school facility energy management and operations today are driven
by a desire to reduce energy use and improve indoor comfort for a campus that
serves more than 18,000 students and 2,000 faculty and staff.
“
Because they’ve approached it so comprehensively, the performance contracting
program provides a way to leverage future avoided utility costs to improve the
comfort, safety, and efficiency of their facilities today,” said Naccarato.
Completing mechanical room installation (L to R) are Doran Hattrick, apprentice plumber, Jim Beatty, service technician, and Brian Duvall, project foreman, Ridgeway Industrial.
According to Siemens, performance contracting permits the University to make
capital improvements to facilities, finance all of the associated costs, and
have a guarantee that the resulting energy savings will cover the debt service.
“It’s a performance-based, design-build energy plan that’s
self-funded by virtue of its own savings,” said Mike Johnson, Siemens project
energy engineer. “Put another way, the debt service created as a result
of the program is retired by the savings generated by the newly applied and/or
installed technologies and operating procedures.”
“We’re making a concerted effort to manage the taxpayers’ funds
responsibly,” says Einar Norton, P.E., the university’s engineer. “We
have taken some major steps and have achieved some really fantastic results.
Full involvement in the performance contract will be the next logical step
in continuing to conserve energy and replace our older equipment.”
Siemens recently completed a comprehensive energy audit. Improvements now
focus on the following:
• New lighting technology and controls
• New HVAC equipment, mechanical systems and automated controls
• Campus-wide trash compacting
• New window technology
• Utility information-management software
• Water conservation
• Individual sub-metering and monitoring
“
The [Boise State] plan is innovative, open and comprehensive in its approach
to reducing utilities consumption, as well as improving the overall learning,
teaching, research and work environment,” said Naccarato. “This
project can serve as a benchmark for universities nationwide.”
Joe Stagg, Columbia Hydronics, performs pre-fire diagnostics.
Busiest spot on campus
More than just a central gathering place for Boise State University’s
student population, the Student Union is the heart of campus life and a major
asset to
the surrounding metropolitan community. Comprising two stories and 185,000
square feet, the facility offers 15 meeting rooms, two divisible ballrooms,
a proscenium
theater, five retail dining establishments with seating for 350, and a game
center with six bowling lanes, billiards tables and video games.
“Approximately 6,500 people travel through the Student Union every day,” says
Leah Barrett, the facility’s director. “More than 10,000 meetings
and events are held here each year, and 350,000 people attend those events.”
“The Student Union operates much like a private hotel,” adds Norton. “When
people pay for a convention center, they wouldn’t be happy to learn that
hot water isn’t available.”
The ability to meet peak demand for domestic hot water was a
growing concern for Norton and the facility’s staff. At 35 years old, the four existing
boilers had reached the end of their useful life. Flue gas condensate acids
were corroding exhaust stacks, and operating efficiency hovered in the range
of 65
to 70 percent. Patching up the system no longer was an option; the facility
was ready for a complete replacement of the boiler systems.
Joe Stagg checks a pressure gauge.
Key project concerns
Installation of the new boilers would not be a simple drop-in replacement.
Because of the constant activity at the Student Union, downtime
would have to be kept
to a minimum, and the new boilers would need to be installed
prior to removal of the existing systems. The major challenge here was finding
boilers
with
a footprint small enough to fit into the existing space.
“Back in the ’60s and ’70s, big buildings were built around
boilers and chillers,” said Charles Paulin, P.E., a co-owner of Musgrove
Engineering, the principal engineering designer on the project. “It’s
nearly impossible to get new equipment into these rooms. So, a big selling
factor in my mind was equipment with a small size that could fit through a
normal door.”
Paulin found his solution in the form of two Pennant fan-assisted,
sealed combustion boilers from Laars Heating Systems, a division
of Waterpik
Technologies, Inc.
At 40” tall, 30” deep and 58” wide, the units were small enough
to fit through the existing doorway, and they were rack-mounted and stacked to
further save floor space, making a full rack height of 95”.
The pump installed on the side of the rack added about 12” to the unit’s
width. Another key attribute of the seismic rack is that the
water heaters can be serviced without being pulled down.
Pre-fire diagnostics are performed before starting the equipment.
According to Joan Mishou, manager of applications engineering,
Laars, the units are designed to maintain a specific water velocity
for
a specific water type,
i.e., for normal, hard and soft water. The company designates
the pump based on specific application and conditions. Once installed,
they
need to be tuned
or set for the proper flow rates to maintain the velocity within
the pipes.
“Pump mounted water heaters can be ordered with standard pump for soft
or normal or with pumps for hard water,” said Mishou “The
pumps used are sized for the head loss through the heater, plus
30 feet of full-sized
piping
(same size as the heater outlet) with, typically, five to six
fittings.
Laars defines the flow rates and head loss that should
be maintained
for each water type and model. Once these are set, the boiler
delivers a consistent
temperature rise through the heat exchanger. With normal water
conditions, each of the Pennant
1000 boilers in the Student Union requires 68 gallons of water
per minute at
3.6 feet of head pressure. The unit delivers a 25°F temperature
rise through the boiler.
Installation is made by (L) Jim Beatty and (R) Doran Hattrick.
Other features also made the Pennant boilers an excellent choice.
At a combined 2 million BTUs (1 million BTUs per unit), the boilers
provided
additional
capacity for a building expansion that is planned for within
the next five
years. The
new units operate at 85 percent efficiency. They offer four-stage
control to meet demand as needed, providing considerable energy
savings. They
also offer
reliability and continuous operation.
In larger Pennant models, where two ignition modules are used
(models 1000, 1500 & 2000,
such as the Pennant 1000’s used in the Student Union), each burner stage
fires independently of one another. This patented design offers balanced air
flow to each stage, enabling operation as individual water heaters. This permits
each unit to continue operation without having to shut down the entire heater.
“It’s like having a built-in stand-by water heater,” Norton
says. “If there would be failure of one of the ignition systems, the other
takes over. That’s unlike any other water heater, and an important factor
for us.”
Local manufacturer representation was another crucial factor,
according to Norton. “I
wouldn’t care if it was the best whizbang product we could have,” he
says. “I wouldn’t want it if no one was here to take care of it.”
Jim Beatty, Ridgeway Industrial service technician, prepared the boiler/water heater unit for startup.
The Boise State team found that support through Columbia Hydronics
Company, which ultimately was awarded the bid contract. In addition
to supplying
the equipment,
Columbia Hydronics’ team, led by Joe Stagg, assisted Musgrove Engineering
with the boiler control design.
“When our Boise office was opened in February 2003, we knew nothing of
this project,” Stagg says. “But in the end, both the engineering
firm and the University were satisfied with our service and performance, as
well as our dedication to our superior equipment.”
A tight deadline
Space limitations were not the only challenging factor in this project. Seamless
installation also played a large role.
“Because we’re such a busy facility that’s integral to the
operation of the campus, having the facility shut down with its water off puts
a significant strain on everything,” Barrett says.
Full switch-over to the new system was scheduled for the 2003
Memorial Day weekend. Hot-water supply was to be turned off Sunday
afternoon,
and everything
had to
be up and running Monday morning.
“Everything worked out so well that even our guys got some time off for
the holiday,” says Brian Duvall, project superintendent for Boise-based
Ridgeway Industrial, Inc., the mechanical contracting firm that was awarded the
installation contract. “We got the equipment there and prefabricated
as much as we could. BSU helped us bleed out the systems. We had to replace
the
waterline valve, but we planned that it might happen and had the equipment
there.
“We had out best foreman on the job, our best journeyman and a very good
apprentice,” added Duvall. “If you have good staff and good clients
to work with, then no challenge is really that difficult.”
“We’re absolutely thrilled with the support we’ve had,” Norton
adds. “The local rep provided fantastic service, and we’ll definitely
spec them again.”
Archives
|