Feature

News

Tech Line

Breaking News

New Products

America's Street Guide

Literature Review

Supplier Directory

Links

Toolbox

Message Board

Archives

The Chief Engineer - HOME

HOME

Contact Us

Subscribe to Magazine

Pay Dues

Join Us

About Us

President's Message November, 2008
 


Wrench

Past Events

Upcoming Events

 
RSS File Feed
RSS File Feed For This Site

For Advertising Information Click Here

Feature  

Committed
 
 

Stay informed of the latest news and important bulletins:

Enter email address and press "GO". Check the "unsubscribe" button to unsubscribe.

subscribe
unsubscribe

Archives

Comprehensive Energy Savings Earns A+

Comprehensive Energy Savings Earns A+

By replacing the Student Union’s boilers with newer, more efficient equipment, Boise State University has taken an important step in improving overall campus operations. In May 2003, the university announced the formation of an energy-‘Performance Contracting’ partnership with Siemens Building Technologies, Inc. Energy Services. This follows already successful efforts by the university to reduce energy costs by $250,000 annually through avoided utility consumption.

According to David Naccarato, Siemens account executive, Boise State’s sweeping initiative is fueled by a desire to steward funds responsibly. Virtually all facets of school facility energy management and operations today are driven by a desire to reduce energy use and improve indoor comfort for a campus that serves more than 18,000 students and 2,000 faculty and staff.

“ Because they’ve approached it so comprehensively, the performance contracting program provides a way to leverage future avoided utility costs to improve the comfort, safety, and efficiency of their facilities today,” said Naccarato.

Completing mechanical room installation (L to R) are Doran Hattrick, apprentice plumber, Jim Beatty, service technician, and Brian Duvall, project foreman, Ridgeway Industrial.

According to Siemens, performance contracting permits the University to make capital improvements to facilities, finance all of the associated costs, and have a guarantee that the resulting energy savings will cover the debt service.

“It’s a performance-based, design-build energy plan that’s self-funded by virtue of its own savings,” said Mike Johnson, Siemens project energy engineer. “Put another way, the debt service created as a result of the program is retired by the savings generated by the newly applied and/or installed technologies and operating procedures.”

“We’re making a concerted effort to manage the taxpayers’ funds responsibly,” says Einar Norton, P.E., the university’s engineer. “We have taken some major steps and have achieved some really fantastic results. Full involvement in the performance contract will be the next logical step in continuing to conserve energy and replace our older equipment.”

Siemens recently completed a comprehensive energy audit. Improvements now focus on the following:

•  New lighting technology and controls

•  New HVAC equipment, mechanical systems and automated controls

•  Campus-wide trash compacting

•  New window technology

•  Utility information-management software

•  Water conservation

•  Individual sub-metering and monitoring

“ The [Boise State] plan is innovative, open and comprehensive in its approach to reducing utilities consumption, as well as improving the overall learning, teaching, research and work environment,” said Naccarato. “This project can serve as a benchmark for universities nationwide.”

Joe Stagg, Columbia Hydronics, performs pre-fire diagnostics.

Busiest spot on campus

More than just a central gathering place for Boise State University’s student population, the Student Union is the heart of campus life and a major asset to the surrounding metropolitan community. Comprising two stories and 185,000 square feet, the facility offers 15 meeting rooms, two divisible ballrooms, a proscenium theater, five retail dining establishments with seating for 350, and a game center with six bowling lanes, billiards tables and video games.

“Approximately 6,500 people travel through the Student Union every day,” says Leah Barrett, the facility’s director. “More than 10,000 meetings and events are held here each year, and 350,000 people attend those events.”

“The Student Union operates much like a private hotel,” adds Norton. “When people pay for a convention center, they wouldn’t be happy to learn that hot water isn’t available.”

The ability to meet peak demand for domestic hot water was a growing concern for Norton and the facility’s staff. At 35 years old, the four existing boilers had reached the end of their useful life. Flue gas condensate acids were corroding exhaust stacks, and operating efficiency hovered in the range of 65 to 70 percent. Patching up the system no longer was an option; the facility was ready for a complete replacement of the boiler systems.

Joe Stagg checks a pressure gauge.

Key project concerns

Installation of the new boilers would not be a simple drop-in replacement. Because of the constant activity at the Student Union, downtime would have to be kept to a minimum, and the new boilers would need to be installed prior to removal of the existing systems. The major challenge here was finding boilers with a footprint small enough to fit into the existing space.

“Back in the ’60s and ’70s, big buildings were built around boilers and chillers,” said Charles Paulin, P.E., a co-owner of Musgrove Engineering, the principal engineering designer on the project. “It’s nearly impossible to get new equipment into these rooms. So, a big selling factor in my mind was equipment with a small size that could fit through a normal door.”

Paulin found his solution in the form of two Pennant fan-assisted, sealed combustion boilers from Laars Heating Systems, a division of Waterpik Technologies, Inc. At 40” tall, 30” deep and 58” wide, the units were small enough to fit through the existing doorway, and they were rack-mounted and stacked to further save floor space, making a full rack height of 95”.

The pump installed on the side of the rack added about 12” to the unit’s width. Another key attribute of the seismic rack is that the water heaters can be serviced without being pulled down.

Pre-fire diagnostics are performed before starting the equipment.

According to Joan Mishou, manager of applications engineering, Laars, the units are designed to maintain a specific water velocity for a specific water type, i.e., for normal, hard and soft water. The company designates the pump based on specific application and conditions. Once installed, they need to be tuned or set for the proper flow rates to maintain the velocity within the pipes.

“Pump mounted water heaters can be ordered with standard pump for soft or normal or with pumps for hard water,” said Mishou “The pumps used are sized for the head loss through the heater, plus 30 feet of full-sized piping (same size as the heater outlet) with, typically, five to six fittings.

Laars defines the flow rates and head loss that should be maintained for each water type and model. Once these are set, the boiler delivers a consistent temperature rise through the heat exchanger. With normal water conditions, each of the Pennant 1000 boilers in the Student Union requires 68 gallons of water per minute at 3.6 feet of head pressure. The unit delivers a 25°F temperature rise through the boiler.

Installation is made by (L) Jim Beatty and (R) Doran Hattrick.

Other features also made the Pennant boilers an excellent choice. At a combined 2 million BTUs (1 million BTUs per unit), the boilers provided additional capacity for a building expansion that is planned for within the next five years. The new units operate at 85 percent efficiency. They offer four-stage control to meet demand as needed, providing considerable energy savings. They also offer reliability and continuous operation.

In larger Pennant models, where two ignition modules are used (models 1000, 1500 & 2000, such as the Pennant 1000’s used in the Student Union), each burner stage fires independently of one another. This patented design offers balanced air flow to each stage, enabling operation as individual water heaters. This permits each unit to continue operation without having to shut down the entire heater.

“It’s like having a built-in stand-by water heater,” Norton says. “If there would be failure of one of the ignition systems, the other takes over. That’s unlike any other water heater, and an important factor for us.”

Local manufacturer representation was another crucial factor, according to Norton. “I wouldn’t care if it was the best whizbang product we could have,” he says. “I wouldn’t want it if no one was here to take care of it.”

Jim Beatty, Ridgeway Industrial service technician, prepared the boiler/water heater unit for startup.

The Boise State team found that support through Columbia Hydronics Company, which ultimately was awarded the bid contract. In addition to supplying the equipment, Columbia Hydronics’ team, led by Joe Stagg, assisted Musgrove Engineering with the boiler control design.

“When our Boise office was opened in February 2003, we knew nothing of this project,” Stagg says. “But in the end, both the engineering firm and the University were satisfied with our service and performance, as well as our dedication to our superior equipment.”

A tight deadline

Space limitations were not the only challenging factor in this project. Seamless installation also played a large role.

“Because we’re such a busy facility that’s integral to the operation of the campus, having the facility shut down with its water off puts a significant strain on everything,” Barrett says.

Full switch-over to the new system was scheduled for the 2003 Memorial Day weekend. Hot-water supply was to be turned off Sunday afternoon, and everything had to be up and running Monday morning.

“Everything worked out so well that even our guys got some time off for the holiday,” says Brian Duvall, project superintendent for Boise-based Ridgeway Industrial, Inc., the mechanical contracting firm that was awarded the installation contract. “We got the equipment there and prefabricated as much as we could. BSU helped us bleed out the systems. We had to replace the waterline valve, but we planned that it might happen and had the equipment there.

“We had out best foreman on the job, our best journeyman and a very good apprentice,” added Duvall. “If you have good staff and good clients to work with, then no challenge is really that difficult.”

“We’re absolutely thrilled with the support we’ve had,” Norton adds. “The local rep provided fantastic service, and we’ll definitely spec them again.”




Archives

Please rate this article:

Not Useful Very Useful


 

Feature :: News :: Tech Line :: Breaking News :: New Products :: America's Street Guide :: Literature Review :: Supplier Directory :: Links :: Toolbox :: Archives
 

Contact Webmaster
 

Chief Engineers Association of Chicagoland
4701 Midlothian Turnpike, Suite 4
Crestwood, IL 60445
Phone: 708.293.1720 Fax: 708.293.1432
Copyright © 2008, Chicagoland Chief Engineer All Rights Reserved
www.chiefengineer.org
 

Internet Marketing - Chicago Web Design by PrairieWeb