|
Archives
Olympic Marvel Is A Tribute To Engineering Ingenuity
When the world watches the opening of the Athens Olympics this month, it will
behold an engineering marvel. The Athens Olympic Stadium has a suspended arched
roof construction, designed by the world-renowned Spanish architect, Santiago
Calatrava. The roof is easily the most visually striking part of the total
refurbishment of the original stadium.
This “jewel in the crown”, as the stadium’s roof has come
to be known, is sure to be the trademark of the 2004 Olympic Games. Its two
giant
arches have a total span of 1,000 feet and soar to a maximum height of 262
feet.
Athen's Oaka Olympic Stadium is being refurbished with two double bowstring tied arches.
Each arch supports the cables that hold the polycarbonate roof panels, which
weigh a total of 17,000 tons and cover an area of 107,500 square feet, covering
the 75,000 spectators and athletes alike. Ninety-five percent of the stadium’s
seating will be covered, as compared to thirty-five percent in the original
stadium.
The graceful sweeping roof structure is constructed of metal and glass with
a special coating designed to reflect 60% of the sun - a feature very important
during the Greek summer. Its unique architectural and structural design makes
it a particularly unique project, because the existing stadium was refurbished
while the roof and arches were being constructed and erected.
The roof structure - the design of which is a double bowstring tied arch
- was assembled close to the sides of the stadium. Arches and roof were constructed
separately in two halves, positioned 230 feet from either side of the stadium.
They were built remotely so as not to interfere with the underlying stadium.
This remote construction, however, gave rise to an important question, namely;
how to move and position the two roof halves, each weighing 8,500 tons.
Double acting pull cylinders are attached to shoes in a sliding and guiding system pulling the arched roof assembly step by step into the final position.
The arched roof is built on two shoes supported by four Teflon sliding pads.
The original plan was to move each roof assembly by pulling it ste-by-step
using long strands, chucks and short-stroke hydraulic jacks. This technique
meant the
structure’s shoes had to slike over thin stainless steel plates welded
onto special rails resting on huge concrete beams.
However, computer simulations highlighted potential problems using strands
to pull the roof into position. It was calculated that, because of significant
elastic
energy stored by the strands, the difference between the static and dynamic
frictions of Teflon and stainless steel could create a stick-slip issue related
to the
relatively high acceleration and stops during each step of the pulling process.
This was unacceptable to the designers, who sought another solution.
Enerpac, Integrated Solutions Specialist, was consulted because of their
expertise in major construction and civil engineering projects. Enerpac is
currently
involved in a number of world-first engineering projects, including the 1,200
foot high
Millau Viaduct in France, the highest bridge in the world.
For the Athens Stadium, Enerpac proposed long stroke-pulling cylinders powered
by PLC-controlled hydraulic pumps. Used for the step-by-step pulling process,
these would have very little impact on the existing design.
Four pulling cylinders were proposed for each shoe of the pulling assembly.
Because each arch had two shoes and each shoe had four sliding pads, this meant
a total
of eight hydraulic cylinders were necessary to move and position each half
of the roof.
A two-stage PLC-controlled pump was specified to power each group of four
cylinders. This arrangement offered full control of speed, acceleration and
deceleration
during hydraulic movement. The PLC control was also necessary to ensure digital
monitoring of the pump parameters. This integrated hydraulic system was designed
to provide smooth movement and positioning of the arch.
During the roof positioning, which took place in May and June, the PLC-controlled
pumps were located on the sides of each arch and carried with them during the
pulling process. Each pump supplied all four cylinders with the same hydraulic
pressure and the same pulling force while the stroke synchronization is assured
by the shoe structural strength. Both pumps were connected with a 1,300-foot
cable and synchronized by the PLC-unit to control the start and stop of the
hydraulic movement of the 8,500-ton roof half.
Very smooth starts and stops (while maintaining an acceptable speed) were
facilitated by using a microprocessor-controlled variable-frequency AC motor
drive. This
unit controlled the electric motor speed, thus controlling the pumps’ oil
flow and therefore the retracting speed of the pulling cylinders.
The PLC-controlled unit was used to vary motor speed (rpm) linearly, within
the operator’s defined time intervals, from a minimum to a maximum and
vice versa. In this way, a very low operational speed was achieved once the
arch movement
was started. The speed was kept low for a period in order to stabilize the
system.
In the next step, the pumps’ oil flow was increased linearly (acceleration
ramp) to ensure a constant and carefully controlled acceleration up to the
pulling speed as defined by the roof design team.
The pulling process continued with the cylinder stroke at a constant speed.
Once the cylinder mounted micro switch detected the end of the plunger stroke,
the
hydraulic system automatically decreased linearly (deceleration ramp). This
reduced cylinder retraction speed to a minimum then stopped the pulling process
altogether.
The process started again after reloading (extending) all cylinders at high
speed.
The Athens Olympic Stadium project shows how integration of hydraulics and
electronics into one system for controlled hydraulic movement can solve important
problems
where conventional and traditional methods fail. With the use of PLC-controlled
systems, hydraulic movements become very simple. reliable and safe. Every step
in the process can be monitored at any time. Advantages of an integrated solution
include:
• Use of double-acting, long stroke pulling cylinders considerably increases
system rigidity, compared with using strands. This reduces the amount of elastic
energy
stored during the start of structure movements. Furthermore, double-acting
cylinders, with their powered extending and retracting, improve the control of
heavy load
in case of unexpected external forces (wind, inertia due to sudden stops, etc).
• PLC-controlled integrated hydraulic solutions make synchronization of
movement and speed control simple and accurate, reducing the risk of additional
stress
in the structure.
• Pulling instead of pushing makes the movement more stable, cancels the
risk of buckling and contains the cylinder size.
• Two stage pumps with a high oil flow consistently reduce the cylinder
reload time.
Archives
|